The Energy Unit
29/12/00 Full steam ahead in the boiler department, freezing weather. 15/12/00 Roof fitted to third tank. 29/12/00
19/09/00 The biome end of the heat exchangers. 16/11/00 Roof installed. Water storage tank
08/09/00 Power transformers arriving. 08/09/00 access road being laid around site.
Two Gas burners, one for standby, there is also a stick wood burner. Lets keep it green.
More being added as building progresses |